All registered Survey & Mapping companies are hereby invited to
submit their competitive quotations for Peshawar Northern Bypass
for the following Scope of Works in accordance with attached
specifications / sketch:-
1) Setting out of centre line & ROW boundary at 100 m interval
including main points of curve i.e. TS/PC/ST/PT for a length of
approx. 25 km.
2) Fixing of ROW concrete markers ~900 Nos.
The rates for setting out of centre line & ROW boundary plus
fixing of ROW markers shall include compensation for supply,
transportation of all material, fixing of precast ROW markers
including excavation / backfilling (compacted) and casting
in-situ concrete base, salary of staff and costs of labour,
tools, profit, overhead, taxes and incidental charges necessary
to complete the work in all respect to the entire satisfaction
of NESPAK and also to meet the requirements of item No. 610 of
NHAs’ Specifications. All survey activities shall be supervised
by NESPAK Surveyors. The completion time shall be 45 days from
date of commencement. Sealed quotation will be received on the
following address by July 6, 2009 at 10:30 hours and will
be opened on the same date at 11:30 hours.
Vice President,
H&TE Division, NESPAK House,
1-C, Block-N, Model Town Extension,
Lahore.
(Download)
Invitation for fixing of ROW Concrete markers for Peshawar
Northern Bypass Project and sketches